Production Team

Summer 2018 / Thursday 1-5 / Room 615

Syllabus

Team Guidelines

Production Schedule

Week Topic Outline
Week 1 Course Introduction, Supplies needed, Grading Procedures, Attendance Policy.
Reform into established teams.
Week 2 Final Revised Animatic is due
Production Schedule is due
Critique on progress of animated scenes
Critique on Backgrounds
Week 3 Critique on progress of animated scenes
Critique on Backgrounds
Comparison to Production Schedule to see if production is on schedule
Redistribute work if falling behind
Week 4 Critique on progress of animated scenes
Critique on Backgrounds
Comparison to Production Schedule to see if production is on schedule
Redistribute work if falling behind
Week 5 Team Grade:
Two fully animated scenes are due, complete with finished backgrounds and sound.
They must be incorporated into the Animatic to be graded
Critique on progress of animated scenes
Critique on Backgrounds
Comparison to Production Schedule to see if production is on schedule
Redistribute work if falling behind
Week 6 Two fully animated scenes are due, complete with finished backgrounds and sound.
They must be incorporated into the Animatic to be graded
Critique on progress of animated scenes
Critique on Backgrounds
Comparison to Production Schedule to see if production is on schedule
Redistribute work if falling behind
Week 7 Two fully animated scenes are due.
They must be incorporated into the Animatic to be graded
Critique on progress of animated scenes
Critique on Backgrounds
Comparison to Production Schedule to see if production is on schedule
Redistribute work if falling behind
Week 8 Two fully animated scenes are due, complete with finished backgrounds and sound.
They must be incorporated into the Animatic to be graded
Critique on progress of animated scenes
All Backgrounds should be finished and distributed
Comparison to Production Schedule to see if production is on schedule
Redistribute work if falling behind
Week 9 Two fully animated scenes are due, complete with finished backgrounds and sound.
They must be incorporated into the Animatic to be graded
Critique on progress of animated scenes
All Backgrounds should be finished and distributed
Comparison to Production Schedule to see if production is on schedule
Redistribute work if falling behind
Week 10 Two fully animated scenes are due, complete with finished backgrounds and sound.
They must be incorporated into the Animatic to be graded
Critique on progress of animated scenes
Comparison to Production Schedule to see if production is on schedule
Redistribute work if falling behind
Week 11 Presentation of Final Project (team grade)
Individual Team Evaluations
Questions